United States · Federal: EPA TSCAPartly in force

TCE: use-specific phaseouts and partial postponement

U.S. EPA trichloroethylene requirements have use-specific phaseouts and selective postponements, including a May 18, 2026 postponement of conditions on section 6(g) exemptions during judicial review. An October 14, 2026 proposal would move the December 18, 2026 prohibition date for listed processing uses and wastewater disposal to December 31, 2027.

Scope to keep in mind

The adopted December 18, 2026 date applies unless EPA finalizes the extension first. Court status comes from EPA notices, and applicable deadlines depend on the specific use.

Legal status
Final rule with selective postponement and interim-final extensions
Source check
Nov 11, 2026
Topic
Trichloroethylene

What changed

Previous requirement

2024 final rule set prohibitions and interim WCPP requirements; initial effective date January 16, 2025 was affected by court and agency delays.

New requirement or current position

May 2026 notice postpones section 6(g) conditions. September 2025 interim rule extends nuclear-fuel processing-aid and specified wastewater-disposal dates.

Who it affects

  • Degreasing
  • Battery separators
  • Nuclear fuel
  • Aviation
  • Chemical manufacturing
  • Environmental laboratories

Dates and milestones

Commencement and compliance dates can differ. Read the conditions beside each date, including any stay or local adoption requirement.

Announcement or publication
May 5, 2026
Recorded effective date
May 18, 2026
Sep 15, 2025

Most industrial/commercial uses under original rule

Do not apply to listed extensions/exemptions.

Dec 18, 2026

Processing TCE as a reactant or intermediate, specified processing-aid uses, and associated wastewater disposal

Wastewater date extended by interim final rule effective September 15, 2025. Adopted date. EPA proposed on October 14, 2026 to move it to December 31, 2027 (91 FR 65149); that change is not final.

Jun 7, 2027

HFC-134a manufacture using TCE

First step-down to no more than 75 percent of baseline. Adopted date. EPA proposed on October 14, 2026 to move it to December 31, 2027 (91 FR 65149); that change is not final.

Sep 15, 2028

TCE processing aid in nuclear-fuel manufacture

Extended prohibition date.

Not established or not applicable

Conditions on section 6(g) exempt uses

Postponed until conclusion of judicial review.

Selected exposure values

These values need the scope, limit type and averaging period shown below. A proposed or advisory value is not a binding limit.

Trichloroethylene

0.2 ppm
Averaging period8-hour TWA
Limit typeInterim TSCA ECEL
ScopeSpecified continuing uses; section 6(g) conditions postponed

Trichloroethylene

0.1 ppm
Averaging period8-hour TWA
Limit typeInterim TSCA ECEL action level
ScopeSpecified continuing uses; section 6(g) conditions postponed

What this could mean for your IH program

Advisory interpretation: Assign a condition-of-use category before exposing any deadline or limit in a facility workflow. A single TCE status badge is inadequate.

Confirm applicability with a qualified practitioner before changing your program.

Questions and qualifications

  • Court docket not independently retrieved (PACER login required). Court status rests on EPA notices: the May 2026 notice describes the Third Circuit's February 11, 2026 order, and the October 2026 proposal notes the consolidated petitions without describing any stay. EPA page link once pointed to unrelated FR 2026-08693; correct notice is 2026-08750. Exemption-specific cessation dates require a separate legal mapping.
  • If no final rule issues before December 18, 2026, that date takes effect as adopted. Recheck status on that date.
  • A separate reconsideration rulemaking (RIN 2070-AL41) covering workplace exposure controls was listed for July 2026 and has not been published.

Source evidence

  1. Trichloroethylene: TSCA final rule

    EPA / Federal Register · 89 FR 102568; IV.C; 751.307

    Rule phases out TCE; interim ECEL 0.2 ppm and action level 0.1 ppm as 8-hour TWAs apply to specified continuing uses, subject to later postponements.

  2. Risk Management for Trichloroethylene

    EPA · Managing Risks; updated October 22, 2026

    Describes the section 6(g) postponement, nuclear-fuel and wastewater extensions, and the October 14, 2026 proposal; states interim workplace protections under the 2024 rule continue to apply during this period. An earlier version linked the postponement notice to unrelated FR 2026-08693; the correct notice is 2026-08750.

  3. TCE: extension of postponement for certain provisions

    EPA / Federal Register · 91 FR 24133; Dates; I Background; II Action

    As of May 18, 2026, conditions imposed on TSCA section 6(g) exemptions postponed until judicial review ends. March 28, 2025 court action lifted stay for other portions; this is not a blanket stay.

  4. TCE: compliance date extension

    EPA / Federal Register · 90 FR 44772; Summary, Dates, amendments

    Published September 17, 2025 but effective September 15, 2025; nuclear fuel processing-aid prohibition September 15, 2028; specified wastewater disposal prohibition December 18, 2026.

  5. TCE: compliance date extensions, proposed rule

    EPA / Federal Register · 91 FR 65148-65154; Dates; Unit I.C (91 FR 65149-65150); 91 FR 65150 (litigation); FR Doc. 2026-20964; RIN 2070-AL45; Docket EPA-HQ-OPPT-2026-7327

    Proposes moving the December 18, 2026 prohibition date for reactant/intermediate processing, listed processing-aid uses and associated wastewater disposal to December 31, 2027 (751.305, 751.313) and the HFC-134a step-down from June 7, 2027 to December 31, 2027 (751.307). Comments due November 13, 2026. Notes the consolidated Third Circuit petitions and EPA's announced reconsideration. ECEL values unchanged.

Managing your IH program

Explore how LEAP IH supports industrial hygiene data management and risk assessment.

Explore LEAP IH

See a missing update or a correction? Contact APT with this page and the official source.